By providing your contact information to Dianne Van Volkenburg, your personal information will be processed in accordance with Dianne Van Volkenburg's Privacy Policy. By checking the box(es) below, you consent to receive communications regarding your real estate inquiries and related marketing and promotional updates in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. You may opt out of receiving further communications from Dianne Van Volkenburg at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe.

Thank you for your message. We will be in touch with you shortly.

Explore Our Properties
Close view of a charcoal front door, fieldstone pier, and broad stone steps beside a burgundy Japanese maple.

Loudoun Data Center Pause: What It Could Mean for Sterling

October 15, 2026

"It is not possible to do a moratorium on data center approvals." Loudoun County Attorney Leo Rogers wrote that in a memo to the Board of Supervisors, as Loudoun Now reported. Rogers said a case from Fairfax County confirmed that Virginia localities cannot stop accepting site plans or subdivision applications.

That memo set the limits of everything since. On September 15, 2026, the Board voted to consider a resolution that would pause its own final votes on data center and electrical substation applications that need legislative approval. The pause would last up to 12 months, the most Virginia law allows. That resolution comes up on October 20, 2026. If it passes, it applies back to September 15. Little of the construction coming to the Sterling area over the next few years depends on the votes that would be paused.

Five Pipelines, Two of Them Paused

Data center and power projects in eastern Loudoun reach approval through different channels. The proposed resolution reaches only the two that end in a Board vote.

Pipeline Who decides Status under the proposed pause
By-right data center applications County staff, administrative review Not affected. About 18.2 million square feet in review continues on its normal schedule
Grandfathered applications under the 2025 rules Protected under the March 2025 grandfathering resolution Protection remains through February 12, 2028. 15 applications totaling 10.5 million square feet qualify
Legislative data center applications Board of Supervisors Final votes deferred up to one year. Applications are still accepted and still go through Planning Commission review
Legislative substation applications Board of Supervisors Included in the pause, though the Board may consider exceptions for grid reliability
High-voltage transmission lines Virginia State Corporation Commission Outside county authority

Even the paused channel has a built-in timer. Under the county's Zoning Ordinance, the one-year clock for a legislative application starts when it goes to a Planning Commission public hearing. Loudoun Now reported that nine data center or substation applications will reach that deadline before September 15, 2027. The Board would have to act on those before their deadlines unless the applicants agree to defer.

The pause also has a stated purpose. It gives the county time to finish its review of data center standards and locations, which amends both the Comprehensive Plan and the Zoning Ordinance and is expected to wrap up in summer 2027. The real policy decision is that rewrite. The pause just holds new legislative cases until it is done.

October 6 Kept the Largest Protected Block in Place

The grandfathered pipeline matters more than the pause. Three weeks after the September vote, it survived a direct challenge.

Supervisors Laura TeKrony and Juli Briskman had proposed ending the grandfathering protections from the county's 2025 data center rules early, before their 2028 sunset. At the October 6 meeting, county staff said revoking those protections would likely bring litigation costing up to $60 million. Betsy Smith, Director of Building and Development, said the change could also affect the county's bond rating. TeKrony then proposed a third-party audit of 30 projects instead. Fifteen had been approved since March 2025 and 15 were under review. The audit would have cost up to $200,000 and reported by April 2027. The Loudoun Times-Mirror reported that the Board tabled the discussion 7-2, with TeKrony and Briskman opposed. The paper also said another related motion from Sterling District Supervisor Koran Saines was expected at the October 20 meeting.

Smith also said one application submitted before the February cutoff, just under 100,000 square feet, did not qualify for grandfathering because the property sits within 500 feet of residential property. Four other applications, totaling 1.8 million square feet, have lost grandfathered status since February 2025. Smith said the status of all of these applications can change until the protections end. So under the county's own rules, distance to homes already decides which projects keep their protection, and that test exists whether or not the pause passes.

Construction is also visible now. Loudoun Now has shown a data center under construction on Maries Road in Sterling. A building already going up is past the stage where any Board pause would apply.

Golden Substation Is Where the Pause Meets Sterling Directly

Golden Substation is the one pending case in Sterling that the resolution could reach. Dominion Energy's application, LEGI-2025-0012, covers a substation between Pacific Boulevard and Route 28 along the W&OD Trail. It is part of a power loop through eastern Loudoun meant to improve grid reliability.

Loudoun Now reported that Supervisor Saines said design changes from a summer working group "aren't enough." He won support to push the vote to December. Dominion warned that more delay "unreasonabl[y] jeopardizes the reliability of the grid." Saines answered that approval would not mean immediate construction: "Let's be real; they're not going to be moving dirt tomorrow if this is approved. They still have to go through a whole lot of other things to get this done."

His point applies to the pause as well. A Board vote is one step in a long sequence, and putting it off moves the date without changing the other steps. The proposed resolution also lets the Board consider exceptions for applications involving grid reliability. Dominion has made that argument about Golden publicly.

The Lines Were Settled in Richmond

The transmission lines connected to Golden were decided by the State Corporation Commission, not by the county. Dominion's project page describes the Loudoun Reliability Loop as three 500/230 kV projects:

  • Aspen to Golden. Filed with the SCC on March 7, 2024, approved February 5, 2025, and affirmed by the Supreme Court of Virginia on February 19, 2026. Dominion says it is in final preparation before construction.
  • Mars to Wishing Star. Approved in April 2023, with energization expected by summer 2026.
  • Golden to Mars. Filed March 28, 2025, with Route 3A approved June 29, 2026.

Loudoun Now's coverage of the Golden to Mars ruling places the new 230 and 500 kV lines starting near Route 28 and the W&OD Trail. The same story says the commission found no proposed undergrounding alternative feasible. Loudoun County and the Loudoun Valley Estates homeowners' associations had backed burying part of the lines. The county's pause covers the Board's own votes on county land-use applications. It does not reach these state approvals.

What August's Sales Can and Cannot Show

It is tempting to look for the pause in home prices. The timing rules that out. The Dulles Area Association of REALTORS® August 2026 report uses Virginia REALTORS® data pulled on September 15, 2026, the same day as the Board's first vote.

Within that window, Sterling's two main ZIP codes moved in opposite directions. In 20165, August sales fell to 25 from 32 a year earlier, and the median sale price rose 8.2% to $670,000. In 20164, sales slipped to 33 from 36, and the median fell 6.8% to $586,900. Countywide, Loudoun recorded 443 sales in August 2026, down 15.5% from a year earlier. Active listings rose 23.3% to 847, and the median price was essentially flat at $765,000.

With a few dozen sales per ZIP code, which homes happened to close in a given month can swing a median by several percentage points. Neither Sterling figure can reflect a resolution that had not been drafted yet. These numbers are useful for sizing up the market, but they offer no evidence about how buyers are pricing data center policy.

Reading a Specific Address Near Route 28

So the question that matters for a particular house is what sits within sight or earshot of it and which pipeline that project is in. A by-right project in staff review keeps moving. A grandfathered application keeps its protection until February 2028 unless its status changes. A legislative application might wait a year and then be judged under rules that have not been written yet. For a power line, the SCC's order is the controlling document.

The county keeps public pages on data centers and proposed transmission lines. Application numbers like Golden's LEGI-2025-0012 can be traced through Board and Planning Commission agendas. The same agenda materials list a second Dulles-area case, Tech Park at Dulles Substation. It is planned south of Old Ox Road, west of Carters School Road and north of the airport, and its status after the September agenda was not confirmed in the sources reviewed here.

Questions Buyers Raise About the Pause

Is the pause in effect today? Not yet. As of October 12, 2026, the Board has voted only to consider a resolution. The vote is set for October 20, and if adopted it would apply back to September 15.

Does the pause cancel any application? No. The county says the pause would not make any application inactive, and developers can keep submitting applications that move through the Planning Commission.

When do grandfathered protections end? The current sunset is February 12, 2028, after the Board tabled the October 6 effort to end them early.

Could the pause delay Golden Substation further? Golden is a legislative substation application, so the pause could reach it. The proposed resolution also lets the Board consider exceptions involving grid reliability, and the Board's December vote is still on the calendar.

At Dianne Van Volkenburg, our work centers on the zoning and land-use records that decide what can be built next to a property. If you are looking at a Sterling address near Route 28, the W&OD Trail or a pending application, request a private consultation and we will go through which approval pipeline each nearby project is in, using the county's own records.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.